请问在定了装卸率的情况下DETENTION 和DEMMURRAGE 该怎么算?
CARGO QUANTITY:1800MT CARGO LOADING AT ANCHORE
L/RATE:1500MT PWWD SHINC
SOF AS FOLW:
FRI:
1945 ARRIVAL PILOT STATION AND NOR TENDERED
1945-2400 WAITTING FOR PILOT
SAT:
0000-0720 DO
0720-0855 POB,INNER ANCHORAGE AND ANCHORED
0855-1100 INWARD DOCUMENT & FORMALIITIES CLEARD
1100-1700 WATTING CARGO
1730-1830 SUVEYOR ON BOARD,DRAFT SURVEYS BUT FAIL
1830-2400 WAITTING CARGO
SUN:
0000-2400 WAITTING CARGO
MON:
000-1700 WATTTING CARGO
1700-1800 BARGE'S DRAFT SURVEY AND COMPLETD
1800-2400 COMMERCE LOADING
TUE:
0000-0400 LOADING
0400-1100 WAITTING CARGO
1100-1200 BARGE'S DRAF SUVEYS AND COMPLETD
1200-23000 LOADING N/TRIMMING N COMPLETED LOADING
请问在这种情况下,DETENTION 和DEMMURAGE 因该怎么计算?LAYTIME 是从星期六还是星期一起算?
另外还有一个问题,如果一个港口作业习惯只做到下午5-6点,那6点以后的至重新开工的时间因该算入LAYTIME 吗?